***Loop 1604 
Super Street Open House/ Meeting was held on Tuesday,
May 25 at 6:00pm at Northwest Park Hills Baptist Church located at
8550 Bowens Crossing directly off Loop 1604.
Map
Meeting Details

                             
Public Comment is being accepted until June 4, 2010 at 5 p.m. regarding the Proposed Loop 1604 Super Street project.

Three different ways to submit comments!

Email your comments

Mail your comments:
Loop 1604 Super Street
Alamo RMA
1222 N. Main Ave
Ste 1000
San Antonio, TX 78212

Fax your comments:
Attn: Loop 1604
Super Street
210-495-5403

 

Loop 1604 Super Street

The Super Street, an operational and safety improvement for the Loop 1604 corridor, from Braun Road to SH 151 and Loop 1604, is designed to help increase the ease of use of this roadway in the highest traffic areas which exist today.

The proposed project is currently under environmental evaluation and information will be updated on this page on a regular basis.

The Loop 1604 Super Street consists for three separate projects to help improve operations and safety on the Northwest and West part of our community.

The first project - improvements at Braun Road, are being environmentally cleared by the Texas Department of Transportation (TxDOT), and TxDOT will handle the construction work on this project.

Curious as to what is being done at Braun Road?  This is Phase 1 of the overall Loop 1604 Super Street work!

Click here to see the plans!   Please note this is a 10 meg file and is best viewed by saving it to your computer.
 


 

Improvements at New Guilbeau to SH 151 are being environmentally cleared by the Alamo Regional Mobility Authority, and should this proposed project move to construction, TxDOT will oversee all construction. This segment is estimated to cost approximately $5.4 Million to construct and funding is under discussion.

The final proposed project, an underpass extending the mainlanes of SH 151 to Alamo Parkway, under Loop 1604, is being environmentally cleared by the Alamo Regional Mobility Authority, and should this proposed project move to construction, TxDOT will oversee this project. This segment is estimated to cost approximately $18 Million to construct, and funds have been identified by the Texas Transportation Commission.
 

Meeting Materials from the May 25, 2010 Open House / Public Meeting

All files below were shown and presented during the May 25, 2010 Public Meeting / Open House on the Proposed Loop 1604 Super Street.

Please note that all documents are Adobe PDF.

Welcome Guide - overview of the stations offered at the Open House / Public Meeting

Loop 1604 Super Street Information - a quick overview of the proposed Super Street improvements

Schematic 1 - Proposed improvements - west of Braun to New Guilbeau
Schematic 2 - Proposed improvements - Shaenfield
Schematic 3 - Proposed improvements - Loop 1604 at SH 151 

Formal Presentation - schematic for the proposed Super Street and discussion of highlights from the draft Categorical Exclusion for the proposed project


Curious to see how the Super Street on Loop 1604 could operate? Check out the videos below!




AM Rush Hour Traffic Simulation



PM Rush Hour Traffic Simulation